Interconnection queue data
Idaho interconnection queue
792 interconnection requests have been filed at points of interconnection in Idaho since 2000, totalling 112 GW. Of that capacity, 3.4% reached commercial operation and 77.9% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 112 GW
- of capacity requested in Idaho since 2000
- 3.4%
- of it reached commercial operation; 77.9% withdrew
- 59 GW
- filed in the last six years (289 requests), of which 33.3% is still in the queue
Which markets Idaho requests sit in
A state is a location, not a market. Requests at Idaho points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| West | 790 | 110 GW | 3.5% | 77.5% | |
| CAISO | 2 | 2 GW | 0.0% | 100.0% |
Process pages: CAISO.
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Other | 223 | 12 GW | 4.5% | 92.5% | |
| Wind | 152 | 13 GW | 8.8% | 78.1% | |
| Hybrid | 136 | 40 GW | 0.5% | 67.1% | |
| Solar | 124 | 9 GW | 6.4% | 83.8% | |
| Gas | 94 | 26 GW | 3.7% | 89.0% | |
| Battery | 63 | 11 GW | 3.5% | 70.6% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 2000500 MW
- 20016 GW
- 200246 MW
- 20032 GW
- 20042 GW
- 20053 GW
- 20061 GW
- 200710 GW
- 200811 GW
- 20092 GW
- 20102 GW
- 2011711 MW
- 2012116 MW
- 2013373 MW
- 20142 GW
- 2015425 MW
- 201661 MW
- 2017789 MW
- 20183 GW
- 20197 GW
- 20204 GW
- 20216 GW
- 202224 GW
- 202312 GW
- 20244 GW
- 202510 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- undefined82 requests in the dataset
- 230kV51 requests in the dataset
- Distribution Feeder49 requests in the dataset
- 138kV42 requests in the dataset
- 34.5kV35 requests in the dataset
- 12.5kV26 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.