CAISO · California · Public-record retrospective
Arco 230 kV: interconnection queue history
Nine of fourteen requests withdrew; five are still in the queue.
GridVision AI ResearchUpdated
Fourteen interconnection requests since 2010: 9 withdrew and 5 remain active.
- Built
- 0
- Withdrawn
- 9
- Still in queue
- 5
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2010-07-31 | ARCO SOLAR STATION | Solar | 300 MW | Withdrawn2011-07-11 |
| 2011-03-31 | CENTRAL VALLEY II SEGS | Solar | 540 MW | Withdrawn2012-03-31 |
| 2015-04-30 | ANCHO CREEK SOLAR | Solar | 200 MW | Withdrawn2015-07-09 |
| 2016-05-02 | ROLLING HILLS SOLAR | Solar | 206.27 MW | Withdrawn2016-07-06 |
| 2018-04-16 | CHALAN SOLAR | Solar + battery | 66.6 MW | Still in queue |
| 2019-04-15 | KINGSROAD HYBRID SOLAR | Solar + battery | 101.78 MW | Still in queue |
| 2019-04-15 | ARCTURUS | Solar + battery | 151.794 MW | Withdrawn2025-03-03 |
| 2020-04-15 | PUFF HYBRID SOLAR | Solar + battery | 101.8 MW | Still in queue |
| 2020-04-15 | HAWKINS SOLAR HYBRID | Solar + battery | 250 MW | Still in queue |
| 2021-04-15 | CALLINAN SOLAR AND STORAGE | Solar + battery | 160.3879 MW | Withdrawn2025-08-01 |
| 2021-04-15 | ARTEMIS | Solar + battery | 412.336 MW | Still in queue |
| 2023-04-17 | Callinan Solar 2 | Solar + battery | 155 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Tule Fog Solar | Solar + battery | 316 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Pepper Grass | Solar + battery | 320 MW | Withdrawn2024-12-02 |
What the record shows
- 2,349 MW of the 3,282 MW filed here withdrew.
- The largest request filed here, 540 MW (solar), withdrew 1.0 years after filing.
- Three requests were filed on 2023-04-17; all of them withdrew.
- Three of the 9 withdrawals came within a year of filing.
- By technology, the requests here were solar + battery 10, solar 4.
- The longest-standing active request here was filed on 2018-04-16.
- The dataset records this point of interconnection under five spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Five requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.