CAISO · California · Public-record retrospective
Pisgah Substation 230 kV: interconnection queue history
Fourteen of seventeen requests withdrew; three are still in the queue.
GridVision AI ResearchUpdated
Seventeen interconnection requests since 2005: 14 withdrew and 3 remain active.
- Built
- 0
- Withdrawn
- 14
- Still in queue
- 3
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2005-05-11 | K ROAD CALICO SOLAR LLC (KRCS) (FKA CALICO SOLAR 1; SES SOLAR ONE) | Solar | 850 MW | Withdrawn2013-06-05 |
| 2006-09-13 | AMBOY | Wind | 400 MW | Withdrawn2006-10-24 |
| 2007-01-16 | DPT BROADWELL LAKE | Solar | 400 MW | Withdrawn2010-05-21 |
| 2007-07-12 | SIBERIA PHASE I SEGS (FKA DPT BROADWELL LAKE II) | Solar | 400 MW | Withdrawn2013-11-06 |
| 2007-07-12 | SIBERIA PHASE II SEGS (FKA DPT 9) | Solar | 400 MW | Withdrawn2014-01-11 |
| 2007-07-16 | SOUTH BRISTOL MOUNTAINS WIND FARM | Solar + wind | 429 MW | Withdrawn2008-11-26 |
| 2007-12-13 | TROY LAKE WIND | Wind | 150 MW | Withdrawn2008-11-26 |
| 2007-12-27 | TRILOBITE SOLAR PROJECT | Solar | 750 MW | Withdrawn2009-12-08 |
| 2008-05-30 | LUDLOW SOLAR 1 | Solar | 280 MW | Withdrawn2008-11-21 |
| 2008-05-30 | ALTA 13 | Solar | 1150 MW | Withdrawn2008-11-26 |
| 2021-04-15 | FITZGIBBONS SOLAR | Solar + battery | 200 MW | Withdrawn2021-08-09 |
| 2021-04-15 | CADY SOLAR | Solar + battery | 312.96 MW | Still in queue |
| 2023-04-17 | Argenta | Solar | 155.76 MW | Still in queue |
| 2023-04-17 | Hacienda | Solar | 156.525 MW | Still in queue |
| 2023-04-17 | Desert Senna Energy Center | Solar + battery | 312 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Yellowfin | Battery | 315 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Cosmos | Battery | 874 MW | Withdrawn2024-12-02 |
What the record shows
- 6,910 MW of the 7,535 MW filed here withdrew.
- The largest request filed here, 1,150 MW (solar), withdrew 0.5 years after filing.
- Five requests were filed on 2023-04-17; 3 withdrew and 2 remain active.
- Five of the 14 withdrawals came within a year of filing.
- By technology, the requests here were solar 9, solar + battery 3, battery 2, wind 2, solar + wind 1.
- The longest-standing active request here was filed on 2021-04-15.
- The dataset records this point of interconnection under seven spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Three requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record