Pisgah Substation 230 kV: interconnection queue history

Fourteen of seventeen requests withdrew; three are still in the queue.

GridVision AI ResearchUpdated

Seventeen interconnection requests since 2005: 14 withdrew and 3 remain active.

Built
0
Withdrawn
14
Still in queue
3

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2005-05-11K ROAD CALICO SOLAR LLC (KRCS) (FKA CALICO SOLAR 1; SES SOLAR ONE)Solar850 MWWithdrawn2013-06-05
2006-09-13AMBOYWind400 MWWithdrawn2006-10-24
2007-01-16DPT BROADWELL LAKESolar400 MWWithdrawn2010-05-21
2007-07-12SIBERIA PHASE I SEGS (FKA DPT BROADWELL LAKE II)Solar400 MWWithdrawn2013-11-06
2007-07-12SIBERIA PHASE II SEGS (FKA DPT 9)Solar400 MWWithdrawn2014-01-11
2007-07-16SOUTH BRISTOL MOUNTAINS WIND FARMSolar + wind429 MWWithdrawn2008-11-26
2007-12-13TROY LAKE WINDWind150 MWWithdrawn2008-11-26
2007-12-27TRILOBITE SOLAR PROJECTSolar750 MWWithdrawn2009-12-08
2008-05-30LUDLOW SOLAR 1Solar280 MWWithdrawn2008-11-21
2008-05-30ALTA 13Solar1150 MWWithdrawn2008-11-26
2021-04-15FITZGIBBONS SOLARSolar + battery200 MWWithdrawn2021-08-09
2021-04-15CADY SOLARSolar + battery312.96 MWStill in queue
2023-04-17ArgentaSolar155.76 MWStill in queue
2023-04-17HaciendaSolar156.525 MWStill in queue
2023-04-17Desert Senna Energy CenterSolar + battery312 MWWithdrawn2024-12-02
2023-04-17YellowfinBattery315 MWWithdrawn2024-12-02
2023-04-17CosmosBattery874 MWWithdrawn2024-12-02

What the record shows

  • 6,910 MW of the 7,535 MW filed here withdrew.
  • The largest request filed here, 1,150 MW (solar), withdrew 0.5 years after filing.
  • Five requests were filed on 2023-04-17; 3 withdrew and 2 remain active.
  • Five of the 14 withdrawals came within a year of filing.
  • By technology, the requests here were solar 9, solar + battery 3, battery 2, wind 2, solar + wind 1.
  • The longest-standing active request here was filed on 2021-04-15.
  • The dataset records this point of interconnection under seven spellings, which are combined here.

What a decision record would have to make explicit

  • None of the resolved requests at this node reached operation, and the public record does not say why.
  • Three requests are unresolved, so the outcome counts at this node can still change.
  • The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.