CAISO · Arizona

Ten years from request to operation, while four neighbours withdrew.

Hoodoo Wash Switchyard 500 kV

Thirteen requests since 2008: two reached commercial operation, five withdrew, and six are still active — one of them since 2014.

Built
2
Withdrawn
5
Still in queue
6

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2008-06-02AGUA CALIENTESolar290 MWBuilt2014-06-10 · 6.0 yrs
2014-04-30WHITE WING RANCH SOLARSolar + battery200 MWStill in queue
2015-04-30PALOMAS SOLAR PROJECTSolar200 MWWithdrawn2016-03-04
2015-04-30MCFARLAND SOLARSolar + battery500 MWBuilt2025-04-09 · 9.9 yrs
2016-03-08AGUA CALIENTE SOLAR 2Solar20 MWStill in queue
2016-05-02BLUE WING RANCH SOLARSolar205.2 MWWithdrawn2017-04-13
2016-05-02RED WING RANCH SOLARSolar205.2 MWWithdrawn2017-03-09
2016-05-02SIGNAL PEAKSolar400 MWWithdrawn2020-07-08
2017-05-01IRONWOOD SOLARSolar + battery250 MWStill in queue
2019-04-15HOODINISolar + battery459.54 MWStill in queue
2020-04-15DATELAND ENERGY COMPLEXSolar + battery237.5 MWStill in queue
2021-04-15WINGED DOVE STORAGEBattery408.5 MWWithdrawn2023-01-13
2021-04-15REMYSolar + battery308 MWStill in queue

What the record shows

  • MCFARLAND SOLAR was filed on 2015-04-30 and reached commercial operation on 2025-04-09 — just under ten years in the queue.
  • PALOMAS SOLAR, filed the same day as MCFARLAND, withdrew within eleven months.
  • All three requests filed on 2016-05-02 withdrew. Two went within a year; SIGNAL PEAK stayed four years before withdrawing in 2020.
  • WHITE WING RANCH SOLAR has been recorded as active since April 2014, longer than either built project took to reach operation.
  • Six of the thirteen requests at this node have no resolved outcome in the dataset.

What a decision record would have to make explicit

  • This node shows the widest spread between request and operation of the four reviewed here, which makes time-in-queue itself a material input to a development decision.
  • Because six requests are unresolved, any comparison at this node has to remain explicitly open rather than concluded.
  • The record shows duration and outcome only. Study results, upgrade costs and siting constraints are not present and remain unknowns.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.