CAISO · California · Public-record retrospective
Vincent Substation 230 kV: interconnection queue history
5,195 MW filed. 188 MW built.
GridVision AI ResearchUpdated
Sixteen interconnection requests since 2006: 2 reached commercial operation, 9 withdrew, and 5 remain active.
- Built
- 2
- Withdrawn
- 9
- Still in queue
- 5
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2006-02-23 | PALMDALE POWER PLANT | Gas | 570 MW | Withdrawn2019-07-22 |
| 2006-04-05 | WINDSTAR I ALTERNATE | Wind + battery | 120 MW | Still in queue |
| 2013-04-30 | PEARBLOSSOM SOLAR | Solar | 9.5 MW | Built2016-12-29 · 3.7 yrs |
| 2015-04-30 | PALMDALE ENERGY | Gas | 130 MW | Withdrawn2019-07-22 |
| 2016-05-02 | SAGEBRUSH SOLAR 2 | Battery | 179 MW | Built2024-09-16 · 8.4 yrs |
| 2018-04-16 | SAGEBRUSH SOLAR 5 | Solar | 223.56 MW | Withdrawn2019-04-30 |
| 2019-04-15 | SAGEBRUSH 6 HYBRID | Solar + battery | 116.01856 MW | Withdrawn2020-04-29 |
| 2019-04-15 | HUMIDOR STORAGE 1 | Battery | 305 MW | Still in queue |
| 2019-04-15 | FORT TEJON SOLAR | Solar + battery | 310.2 MW | Withdrawn2021-05-05 |
| 2019-04-15 | UNA LAKE SOLAR | Solar + battery | 627 MW | Withdrawn2019-07-10 |
| 2021-04-15 | FLEA FLICKER ENERGY STORAGE | Battery | 213.55 MW | Withdrawn2024-07-31 |
| 2021-04-15 | MAATHAI | Battery | 256 MW | Withdrawn2025-11-18 |
| 2021-04-15 | HUXLEY SOLAR | Solar + battery | 335.7 MW | Withdrawn2021-10-12 |
| 2021-04-15 | SAGEBRUSH ENERGY STORAGE | Battery | 528 MW | Still in queue |
| 2023-04-17 | Rover | Battery | 206.24 MW | Still in queue |
| 2023-04-17 | Hillside Energy Storage | Battery | 1064.748473 MW | Still in queue |
What the record shows
- 2,782 MW of the 5,195 MW filed here withdrew, and 188 MW reached commercial operation.
- Completions here took between 3.7 and 8.4 years from request to commercial operation (median 6.0).
- The largest request filed here, 1,065 MW (battery), was filed in 2023 and is still active.
- Four requests were filed on 2021-04-15; 3 withdrew and 1 remains active.
- Two of the 9 withdrawals came within a year of filing.
- By technology, the requests here were battery 7, solar + battery 4, gas 2, solar 2, wind + battery 1.
- The longest-standing active request here was filed on 2006-04-05.
- The dataset records this point of interconnection under five spellings, which are combined here.
What a decision record would have to make explicit
- What separated the requests that reached operation from those that withdrew, such as study results, upgrade assignments or site conditions, is not in the public queue record, so a decision record here would have to carry it as an unknown.
- Five requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.