CAISO · California
The largest request here withdrew. The smallest, 100 MW, was built.
Victor Substation 230 kV
Six interconnection requests since 2010: 1 reached commercial operation, 5 withdrew.
- Built
- 1
- Withdrawn
- 5
- Still in queue
- 0
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2010-02-01 | BARSTOW SOLAR II | Solar | 420 MW | Withdrawn2010-05-26 |
| 2017-05-01 | HIGH 5 SOLAR | Solar + battery | 100 MW | Built2021-12-08 · 4.6 yrs |
| 2018-04-16 | BIG BEAR WIND | Wind | 199 MW | Withdrawn2018-07-31 |
| 2023-04-17 | Scorpio Storage | Battery | 600 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Luna | Battery | 417 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Titan Power | Battery | 1160 MW | Withdrawn2024-12-02 |
What the record shows
- Five of the six requests at this node withdrew, and 2,796 MW of the 2,896 MW filed here never reached operation.
- The one project that reached operation, 100 MW of solar + battery, took 4.6 years from request to commercial operation.
- The largest request ever filed here, 1160 MW, withdrew 1.6 years after filing.
- Three requests were filed on 2023-04-17, and all of them withdrew.
- Four technologies were filed here: Solar, Solar + battery, Wind and battery.
What a decision record would have to make explicit
- With six requests, nothing at this node generalises to another; it is a record, not a rate.
- The dataset records no withdrawal reasons, study costs or upgrade assignments, so those remain unknowns on this record.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.