CAISO · California · Public-record retrospective
Lamont Substation 115 kV: interconnection queue history
Eight of eleven requests withdrew; three are still in the queue.
GridVision AI ResearchUpdated
Eleven interconnection requests since 2010: 8 withdrew and 3 remain active.
- Built
- 0
- Withdrawn
- 8
- Still in queue
- 3
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2010-01-06 | FRV CYGNUS SOLAR | Solar | 20 MW | Withdrawn2010-04-19 |
| 2011-03-31 | REDWOOD SOLAR FARM | Solar | 90 MW | Still in queue |
| 2015-04-30 | WHITE WOLF SOLAR | Solar | 100 MW | Withdrawn2018-05-16 |
| 2020-04-15 | CRYSTAL FLATS | Solar + battery | 103.455 MW | Still in queue |
| 2021-04-15 | BRECKENRIDGE | Battery | 76.5 MW | Withdrawn2023-01-17 |
| 2021-04-15 | EIGER ENERGY STORAGE | Battery | 100.9 MW | Still in queue |
| 2021-04-15 | ESTRADA STORAGE | Battery | 101.9 MW | Withdrawn2022-12-19 |
| 2021-04-15 | THUNDER | Solar + battery | 102.288542 MW | Withdrawn2023-01-17 |
| 2023-04-17 | Driller Storage | Battery | 102 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Urogallo Storage | Battery | 207 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Eastside Plains Energy Center | Solar + battery | 392 MW | Withdrawn2024-12-02 |
What the record shows
- 1,102 MW of the 1,396 MW filed here withdrew.
- The largest request filed here, 392 MW (solar + battery), withdrew 1.6 years after filing.
- Four requests were filed on 2021-04-15; 3 withdrew and 1 remains active.
- One of the 8 withdrawals came within a year of filing.
- By technology, the requests here were battery 5, solar 3, solar + battery 3.
- The longest-standing active request here was filed on 2011-03-31.
- The dataset records this point of interconnection under six spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Three requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.