CAISO · California · Public-record retrospective
Borrego Substation 69 kV: interconnection queue history
442 MW filed. 26 MW built.
GridVision AI ResearchUpdated
Eleven interconnection requests since 2008: 1 reached commercial operation and 10 withdrew.
- Built
- 1
- Withdrawn
- 10
- Still in queue
- 0
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2008-04-07 | BORREGO STARLIGHT 1 | Solar | 75 MW | Withdrawn2008-11-21 |
| 2008-04-18 | BORREGO SOLAR I | Solar | 26 MW | Built2013-02-12 · 4.8 yrs |
| 2008-05-30 | BORREGO SOLAR 2 | Solar | 49.5 MW | Withdrawn2009-12-11 |
| 2008-06-02 | GREENLIGHT SOLAR I | Solar | 58.8 MW | Withdrawn2008-11-25 |
| 2009-03-16 | 20 MW SOLAR PROJECT #1 | Solar | 20 MW | Withdrawn2013-06-12 |
| 2009-08-21 | FRV PEGASUS SOLAR PROJECT | Solar | 20 MW | Withdrawn2010-05-25 |
| 2011-03-31 | EGP SOLAR 1 | Solar | 28 MW | Withdrawn2012-01-19 |
| 2011-03-31 | BIG HORN 30MW PV PROJECT | Solar | 30 MW | Withdrawn2012-02-01 |
| 2011-03-31 | EE BORREGO II | Solar | 45 MW | Withdrawn2012-03-13 |
| 2011-03-31 | RE PADRE | Solar | 60 MW | Withdrawn2012-02-28 |
| 2020-04-15 | CUCKOO ENERGY STORAGE | Battery | 30 MW | Withdrawn2020-07-03 |
What the record shows
- 416 MW of the 442 MW filed here withdrew, and 26 MW reached commercial operation.
- The one request that reached operation took 4.8 years from request to commercial operation.
- The largest request filed here, 75 MW (solar), withdrew 0.6 years after filing.
- Four requests were filed on 2011-03-31; all of them withdrew.
- Eight of the 10 withdrawals came within a year of filing.
- By technology, the requests here were solar 10, battery 1.
- The dataset records this point of interconnection under five spellings, which are combined here.
What a decision record would have to make explicit
- What separated the requests that reached operation from those that withdrew, such as study results, upgrade assignments or site conditions, is not in the public queue record, so a decision record here would have to carry it as an unknown.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.