Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Monthly generator record

What actually gets built

The queue pages on this site read who asked to connect. This one reads the other end: the generators that reached commercial operation, and the ones plant owners currently report as under construction. Figures come from the July 2026 release of the U.S. Energy Information Administration's monthly generator inventory, and are refreshed when EIA publishes the next one.

GridVision AI ResearchPublished Updated

Headline figures

168.6 GW
reached commercial operation in the 36 months to July 2026, across 3,272 generators
98.4 GW
is reported as under construction, in 1,017 generators
192.7 GW
is planned but not under construction: approvals pending, received or not yet sought

Capacity reaching operation, by month

  • Jul 20235.5 GW
  • Aug 20231.3 GW
  • Sep 20232.7 GW
  • Oct 20233.0 GW
  • Nov 20232.4 GW
  • Dec 202312.8 GW
  • Jan 20243.8 GW
  • Feb 2024881 MW
  • Mar 20244.2 GW
  • Apr 20244.2 GW
  • May 20244.0 GW
  • Jun 20244.4 GW
  • Jul 20243.3 GW
  • Aug 20242.9 GW
  • Sep 20243.3 GW
  • Oct 20243.9 GW
  • Nov 20246.2 GW
  • Dec 202410.0 GW
  • Jan 20255.0 GW
  • Feb 20252.1 GW
  • Mar 20253.8 GW
  • Apr 20253.9 GW
  • May 20254.3 GW
  • Jun 20255.8 GW
  • Jul 20253.4 GW
  • Aug 20254.7 GW
  • Sep 20253.7 GW
  • Oct 20254.4 GW
  • Nov 20254.6 GW
  • Dec 202512.0 GW
  • Jan 20264.0 GW
  • Feb 20261.8 GW
  • Mar 20262.9 GW
  • Apr 20267.7 GW
  • May 20266.8 GW
  • Jun 20266.3 GW
  • Jul 20263.0 GW

The last 3 months are drawn faint because they are still being reported: a generator that started recently may not be on the form yet, so those bars will grow in later releases. EIA also revises earlier months without notice.

By technology

Reached operation in the last 36 months

Capacity online by technology, last 36 months
TechnologyGeneratorsCapacityShare of capacity
Solar2,16387.8 GW52.0%
Battery60042.6 GW25.3%
Wind9721.6 GW12.8%
Gas31014.0 GW8.3%
Nuclear22.2 GW1.3%
Other87293 MW0.2%
Geothermal684 MW0.0%
Hydro615 MW0.0%
Coal110 MW0.0%

Under construction now

Capacity under construction by technology
TechnologyGeneratorsCapacityShare of capacity
Solar59246.8 GW47.6%
Battery23422.8 GW23.2%
Wind3915.2 GW15.5%
Gas10113.2 GW13.4%
Other36190 MW0.2%
Geothermal4131 MW0.1%
Hydro1118 MW0.0%

Groups follow EIA's own technology labels. Other covers the rest — in the July 2026 release, petroleum liquids, biomass, landfill gas and municipal solid waste.

Where it is being built

The twelve states with the most capacity under construction. Where a state has a queue page on this site, its name links to it, so the two records can be read side by side.

StateGeneratorsCapacity
Texas16532.4 GW
California1347.2 GW
Arizona416.3 GW
Michigan273.6 GW
Virginia213.6 GW
Wyoming43.6 GW
Arkansas143.5 GW
New York823.3 GW
Colorado343.2 GW
Illinois1122.9 GW
Oklahoma122.5 GW
Nevada82.3 GW

And where it reached operation in the last 36 months

StateGeneratorsCapacity
Texas46344.0 GW
California40219.1 GW
Arizona9713.6 GW
New Mexico537.1 GW
Florida1076.7 GW
Indiana415.5 GW
Illinois3285.4 GW
Ohio555.2 GW
Georgia344.2 GW
Utah353.9 GW
Nevada373.7 GW
Oklahoma202.9 GW

When construction is planned to finish

For capacity currently under construction, the operation year the owner has on file. This is a plan reported to a federal form, not a prediction, and not a schedule anyone is bound to.

  • 202650.3 GW
  • 202733.3 GW
  • 20286.8 GW
  • 20292.8 GW
  • 2030917 MW
  • 20311.7 GW
  • 20321.3 GW
  • 2033554 MW
  • 2034778 MW

Years carrying under 100 MW are left off this chart; the CSV has every one.

A different record from the queue pages

This page and the queue statistics describe the same industry from opposite ends, and their numbers are not interchangeable. The queue data counts requests: a position in a study process, which may be withdrawn, may be resubmitted, and may cover a project that never existed as a machine. This page counts generators: physical units of 1 MW or more, on a monthly federal inventory.

One project can be several generators, and one queue request can become none. So the two must never be added, subtracted or divided into each other — a completion rate built from a queue numerator and an inventory denominator would be meaningless. Read them as two independent readings: the queue says what was asked for, this says what exists.

Method and limits

Each generator is counted once at its nameplate capacity. "Under construction" and "planned" are the status the plant owner reported to EIA in this release, not an assessment by anyone else and not a forecast. Figures cover the 50 states and the District of Columbia; Puerto Rico sits on separate sheets of the form and is left out here, as it is from the queue record the rest of the site reads.

The form excludes generators below 1 MW. For solar in particular that is a large exclusion — rooftop and small commercial systems are simply not here — so every total on this page is a floor, not a full count.

Figures are preliminary and EIA corrects them in later releases without notice. Older monthly releases live in an archive directory that EIA's robots file asks automated readers not to fetch, so this page carries the current release only; its history builds up one month at a time from here.

Source: U.S. Energy Information Administration, Preliminary Monthly Electric Generator Inventory (EIA-860M), July 2026 release. Public domain. Read September 19, 2026. Downloads: open data and citation.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.