Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

New York interconnection queue

1,882 interconnection requests have been filed at points of interconnection in New York since 2000, totalling 365 GW. Of that capacity, 6.9% reached commercial operation and 86.1% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

365 GW
of capacity requested in New York since 2000
6.9%
of it reached commercial operation; 86.1% withdrew
239 GW
filed in the last six years (1,134 requests), of which 8.4% is still in the queue

Which markets New York requests sit in

A state is a location, not a market. Requests at New York points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
NYISO1,874361 GW6.7%86.3%
ISO-NE84 GW25.6%62.7%

Process pages: NYISO, ISO-NE.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Battery68898 GW0.5%88.2%
Solar46230 GW4.1%76.3%
Wind341141 GW4.2%90.7%
Other15236 GW2.2%97.8%
Gas13342 GW34.8%65.2%
Hybrid10618 GW12.0%79.7%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 200015 GW
  • 20019 GW
  • 20023 GW
  • 20034 GW
  • 20042 GW
  • 20057 GW
  • 20066 GW
  • 20078 GW
  • 200814 GW
  • 20092 GW
  • 20101 GW
  • 20111 GW
  • 20123 GW
  • 20131 GW
  • 20145 GW
  • 20154 GW
  • 20163 GW
  • 20174 GW
  • 201815 GW
  • 201917 GW
  • 202027 GW
  • 202124 GW
  • 202256 GW
  • 202338 GW
  • 202476 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Willis-Plattsburgh WP-2 230kV9 requests in the dataset
  • Holtsville8 requests in the dataset
  • Astoria 138kV6 requests in the dataset
  • 34.5kV6 requests in the dataset
  • Ruland Road 138kV6 requests in the dataset
  • Gowanus 345kV6 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.