Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Georgia interconnection queue

692 interconnection requests have been filed at points of interconnection in Georgia since 2001, totalling 125 GW. Of that capacity, 8.2% reached commercial operation and 54.4% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

125 GW
of capacity requested in Georgia since 2001
8.2%
of it reached commercial operation; 54.4% withdrew
70 GW
filed in the last six years (330 requests), of which 60.5% is still in the queue

Which markets Georgia requests sit in

A state is a location, not a market. Requests at Georgia points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
Southeast692125 GW8.2%54.4%

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Solar43847 GW5.5%61.3%
Gas8144 GW12.5%51.7%
Hybrid7913 GW0.0%40.6%
Battery6214 GW0.5%45.9%
Other317 GW29.2%65.9%
Wind1112 MW0.0%100.0%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 2001581 MW
  • 20033 GW
  • 20052 GW
  • 2006700 MW
  • 20073 GW
  • 2008528 MW
  • 200911 MW
  • 20108 GW
  • 20115 GW
  • 20121 GW
  • 20131 GW
  • 20143 GW
  • 2015185 MW
  • 20167 GW
  • 20176 GW
  • 20186 GW
  • 20197 GW
  • 20207 GW
  • 20216 GW
  • 20226 GW
  • 202320 GW
  • 202418 GW
  • 202513 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • East Bainbridge - Spring Creek (Black) 115 kV Line9 requests in the dataset
  • North Americus - Perry 115 kV Line9 requests in the dataset
  • North Tifton - Pitts 230 kV Line9 requests in the dataset
  • Mitchell - Moultrie 115 kV Line7 requests in the dataset
  • McIntosh Substation 230 kV Bus7 requests in the dataset
  • Bonaire Primary - Eastman Primary 115 kV Line7 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.