Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Florida interconnection queue

907 interconnection requests have been filed at points of interconnection in Florida since 2000, totalling 123 GW. Of that capacity, 18.7% reached commercial operation and 61.6% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

123 GW
of capacity requested in Florida since 2000
18.7%
of it reached commercial operation; 61.6% withdrew
35 GW
filed in the last six years (408 requests), of which 50.5% is still in the queue

Which markets Florida requests sit in

A state is a location, not a market. Requests at Florida points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
Southeast907123 GW18.7%61.6%

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Solar68449 GW20.3%47.5%
Gas11852 GW22.5%70.9%
Other5213 GW6.1%74.0%
Battery337 GW7.6%65.9%
Hybrid202 GW0.0%69.0%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 20004 GW
  • 2001902 MW
  • 20023 GW
  • 2003750 MW
  • 20043 GW
  • 20054 GW
  • 20063 GW
  • 20078 GW
  • 200810 GW
  • 2009288 MW
  • 20102 GW
  • 20115 GW
  • 20123 GW
  • 20133 GW
  • 20141 GW
  • 2015612 MW
  • 201611 GW
  • 201710 GW
  • 20189 GW
  • 20196 GW
  • 20204 GW
  • 20213 GW
  • 20228 GW
  • 202311 GW
  • 20247 GW
  • 20251 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Near LaBelle34 requests in the dataset
  • Pebbledale Substation, Polk County, Florida17 requests in the dataset
  • Northern St. Lucie County16 requests in the dataset
  • State Road 7016 requests in the dataset
  • State Road 8014 requests in the dataset
  • Hines Substation12 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.