ISO-NE · Market-wide
The built share barely moved — and no completion date is recorded at all.
Market-wide queue vintages, 2014–2019
Six years of ISO-NE interconnection requests: the share reaching commercial operation stayed between 17% and 28%, while the dataset records no in-service date for any ISO-NE project.
- Built
- 94
- Withdrawn
- 291
- Still in queue
- 18
The queue record
Every request this market received in each year, and how those requests had resolved by the end of the dataset.
| Filed | Requests | Built | Withdrawn | Still in queue | Median years to build |
|---|---|---|---|---|---|
| 2014 | 39 | 11(28%) | 28 | 0 | N/A |
| 2015 | 63 | 16(25%) | 46 | 1 | N/A |
| 2016 | 31 | 7(23%) | 22 | 2 | N/A |
| 2017 | 54 | 9(17%) | 42 | 3 | N/A |
| 2018 | 117 | 28(24%) | 84 | 5 | N/A |
| 2019 | 99 | 23(23%) | 69 | 7 | N/A |
What the record shows
- ISO-NE received 39 interconnection requests in 2014 and 99 in 2019, peaking at 117 in 2018.
- The built share stayed in a narrow band across all six vintages, between 17% and 28%.
- Withdrawals outnumbered completions in every vintage, by between two and five times.
- None of the 228 ISO-NE requests recorded as operational carries an in-service date, so no time from request to operation can be computed for this market.
- Fewer requests were left unresolved here than in the other markets in this set: 18 across six vintages.
What a decision record would have to make explicit
- Because no in-service date is recorded for this market, ISO-NE cannot be compared with the others on time in queue. The column is shown as N/A rather than estimated.
- ISO-NE is the only market in this set whose built share does not fall across these vintages, but a flat share over six years is a description, not a trend that can be projected forward.
- The dataset records no withdrawal reasons.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.