Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Maine interconnection queue

284 interconnection requests have been filed at points of interconnection in Maine since 2001, totalling 22 GW. Of that capacity, 9.7% reached commercial operation and 85.7% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

22 GW
of capacity requested in Maine since 2001
9.7%
of it reached commercial operation; 85.7% withdrew
8 GW
filed in the last six years (146 requests), of which 12.5% is still in the queue

Which markets Maine requests sit in

A state is a location, not a market. Requests at Maine points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
ISO-NE28422 GW9.7%85.7%

Process pages: ISO-NE.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Solar1145 GW6.6%76.1%
Wind9313 GW7.8%92.0%
Hybrid372 GW11.6%79.5%
Other23515 MW75.1%24.9%
Battery122 GW10.4%89.6%
Gas584 MW11.9%88.1%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 2001126 MW
  • 2005211 MW
  • 200644 MW
  • 2007172 MW
  • 20082 GW
  • 2009503 MW
  • 2010409 MW
  • 2011338 MW
  • 2012270 MW
  • 2013368 MW
  • 20142 GW
  • 20151 GW
  • 20161 GW
  • 20172 GW
  • 20183 GW
  • 2019823 MW
  • 20202 GW
  • 2021822 MW
  • 20223 GW
  • 20231 GW
  • 2024530 MW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • CMP Larrabee Road Station 345 kV8 requests in the dataset
  • Pittsfield 345KV6 requests in the dataset
  • PITTSFIELD 345KV on line 30235 requests in the dataset
  • BHE's Line 5 - 46 kV3 requests in the dataset
  • BHE Keene Road Substation3 requests in the dataset
  • CMP Gulf Island 115 kV3 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Published retrospectives in Maine

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.