Interconnection queue data
Wisconsin interconnection queue
420 interconnection requests have been filed at points of interconnection in Wisconsin since 2000, totalling 84 GW. Of that capacity, 9.5% reached commercial operation and 58.7% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 84 GW
- of capacity requested in Wisconsin since 2000
- 9.5%
- of it reached commercial operation; 58.7% withdrew
- 34 GW
- filed in the last six years (170 requests), of which 70.0% is still in the queue
Which markets Wisconsin requests sit in
A state is a location, not a market. Requests at Wisconsin points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| MISO | 420 | 84 GW | 9.5% | 58.7% |
Process pages: MISO.
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 123 | 18 GW | 8.0% | 43.8% | |
| Wind | 98 | 11 GW | 12.6% | 71.7% | |
| Other | 68 | 19 GW | 11.6% | 88.3% | |
| Gas | 66 | 28 GW | 10.2% | 46.6% | |
| Battery | 47 | 6 GW | 0.0% | 54.5% | |
| Hybrid | 18 | 1 GW | 0.0% | 17.9% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 200011 GW
- 20017 GW
- 20022 GW
- 20033 GW
- 2004510 MW
- 20053 GW
- 2006609 MW
- 2007627 MW
- 20082 GW
- 2009341 MW
- 2010749 MW
- 2011354 MW
- 2012679 MW
- 20131 GW
- 20145 GW
- 20151 GW
- 20162 GW
- 20173 GW
- 20184 GW
- 20192 GW
- 20205 GW
- 20214 GW
- 20228 GW
- 2023200 MW
- 20244 GW
- 202512 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Werner West - Rocky Run 345kV6 requests in the dataset
- Acadian - Forest Junction 345kV3 requests in the dataset
- Dells Hydro Plant3 requests in the dataset
- Sand Lake 138kV Substation3 requests in the dataset
- Hill Valley 345kV3 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.