Interconnection queue data
South Carolina interconnection queue
596 interconnection requests have been filed at points of interconnection in South Carolina since 2001, totalling 65 GW. Of that capacity, 10.7% reached commercial operation and 64.9% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 65 GW
- of capacity requested in South Carolina since 2001
- 10.7%
- of it reached commercial operation; 64.9% withdrew
- 42 GW
- filed in the last six years (404 requests), of which 36.5% is still in the queue
Which markets South Carolina requests sit in
A state is a location, not a market. Requests at South Carolina points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Southeast | 596 | 65 GW | 10.7% | 64.9% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 429 | 29 GW | 2.8% | 76.6% | |
| Gas | 62 | 21 GW | 5.5% | 61.1% | |
| Other | 43 | 7 GW | 67.6% | 23.0% | |
| Battery | 42 | 6 GW | 0.0% | 66.5% | |
| Hybrid | 20 | 2 GW | 1.0% | 83.2% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 20016 GW
- 2003450 MW
- 20051 GW
- 20071 GW
- 2008252 MW
- 2009107 MW
- 2011125 MW
- 201225 MW
- 201428 MW
- 2015387 MW
- 2016364 MW
- 20173 GW
- 20189 GW
- 20191 GW
- 20205 GW
- 20213 GW
- 20227 GW
- 20238 GW
- 202410 GW
- 202510 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- OLANTA 230KV9 requests in the dataset
- Clark Hill7 requests in the dataset
- ROBINSON PLANT - CAMDEN JUNCTION 115KV6 requests in the dataset
- BENNETTSVILLE SW STA - LAURINBURG 230KV5 requests in the dataset
- (blank)5 requests in the dataset
- Clinton4 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.