Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Rhode Island interconnection queue

112 interconnection requests have been filed at points of interconnection in Rhode Island since 2003, totalling 12 GW. Of that capacity, 9.2% reached commercial operation and 82.9% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

12 GW
of capacity requested in Rhode Island since 2003
9.2%
of it reached commercial operation; 82.9% withdrew
5 GW
filed in the last six years (65 requests), of which 4.3% is still in the queue

Which markets Rhode Island requests sit in

A state is a location, not a market. Requests at Rhode Island points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
ISO-NE11212 GW9.2%82.9%

Process pages: ISO-NE.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Solar58687 MW21.5%78.5%
Battery193 GW0.0%92.2%
Gas133 GW26.9%73.1%
Wind114 GW1.3%80.6%
Hybrid72 GW0.0%95.7%
Other463 MW50.8%49.2%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 20034 MW
  • 2006345 MW
  • 2007475 MW
  • 2008868 MW
  • 200949 MW
  • 20102 GW
  • 201329 MW
  • 20153 GW
  • 201661 MW
  • 201795 MW
  • 20181 GW
  • 2019445 MW
  • 2020543 MW
  • 2021635 MW
  • 2022490 MW
  • 2023319 MW
  • 20242 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • kV RISE Substation3 requests in the dataset
  • GRID 115 kV Franklin substation3 requests in the dataset
  • NGRID 345kV Sherman Road (existing OSP I and II switchyard)3 requests in the dataset
  • GRID L-190 line via new station3 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.