Interconnection queue data
Oregon interconnection queue
1,485 interconnection requests have been filed at points of interconnection in Oregon since 2000, totalling 240 GW. Of that capacity, 3.1% reached commercial operation and 61.1% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 240 GW
- of capacity requested in Oregon since 2000
- 3.1%
- of it reached commercial operation; 61.1% withdrew
- 157 GW
- filed in the last six years (583 requests), of which 45.2% is still in the queue
Which markets Oregon requests sit in
A state is a location, not a market. Requests at Oregon points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| West | 1,485 | 240 GW | 3.1% | 61.1% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 485 | 28 GW | 2.9% | 67.7% | |
| Hybrid | 320 | 93 GW | 0.1% | 58.9% | |
| Wind | 307 | 46 GW | 8.9% | 68.9% | |
| Other | 152 | 6 GW | 7.6% | 56.6% | |
| Battery | 149 | 46 GW | 1.3% | 48.6% | |
| Gas | 72 | 21 GW | 6.8% | 74.6% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 20003 GW
- 20018 GW
- 20025 GW
- 20032 GW
- 20042 GW
- 2005817 MW
- 20062 GW
- 20076 GW
- 20088 GW
- 20096 GW
- 20107 GW
- 20114 GW
- 20122 GW
- 20131 GW
- 20142 GW
- 20152 GW
- 20166 GW
- 20174 GW
- 20187 GW
- 20195 GW
- 20209 GW
- 202121 GW
- 202244 GW
- 202367 GW
- 20249 GW
- 20258 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- 138kV17 requests in the dataset
- Hinkle substation17 requests in the dataset
- Ponderosa substation17 requests in the dataset
- 69kV14 requests in the dataset
- Bullard substation14 requests in the dataset
- Corral substation13 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.