Interconnection queue data
Alabama interconnection queue
481 interconnection requests have been filed at points of interconnection in Alabama since 2000, totalling 98 GW. Of that capacity, 3.3% reached commercial operation and 82.0% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 98 GW
- of capacity requested in Alabama since 2000
- 3.3%
- of it reached commercial operation; 82.0% withdrew
- 35 GW
- filed in the last six years (240 requests), of which 37.8% is still in the queue
Which markets Alabama requests sit in
A state is a location, not a market. Requests at Alabama points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Southeast | 481 | 98 GW | 3.3% | 82.0% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 261 | 26 GW | 1.6% | 80.4% | |
| Hybrid | 115 | 14 GW | 0.0% | 77.4% | |
| Other | 53 | 39 GW | 4.4% | 94.0% | |
| Gas | 38 | 16 GW | 6.6% | 66.6% | |
| Battery | 10 | 2 GW | 0.0% | 24.0% | |
| Wind | 4 | 358 MW | 0.0% | 100.0% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 20007 GW
- 20016 GW
- 20022 GW
- 20039 GW
- 20042 GW
- 20055 GW
- 2007667 MW
- 20086 GW
- 201052 MW
- 20112 GW
- 20122 GW
- 2013442 MW
- 2014874 MW
- 2015700 MW
- 20164 GW
- 20171 GW
- 20182 GW
- 20198 GW
- 20209 GW
- 20213 GW
- 20226 GW
- 20238 GW
- 20243 GW
- 20257 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Greene County - North Selma 230 kV Line23 requests in the dataset
- Greenville - Pintlala 115 kV Line12 requests in the dataset
- Demopolis - Selma 115 kV Line10 requests in the dataset
- Bucks SS - North Brewton 230 kV Line9 requests in the dataset
- Greene County - Octagon 115 kV Line8 requests in the dataset
- Goat Rock Substation 230 kV Bus7 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Want this reading for a Alabama point of interconnection?
Send the node and the market. We read the public queue record for it — what was filed, what was built, what withdrew and how long each took — and send back what the record does and does not show.
Ask for a node retrospectivePublic-record reading only. Management review and formal interconnection studies remain authoritative.